Please be advised that scheduled works, which require localised road closures along Rokeby Road, will take place until Wednesday 22 February. Working at night in order to minimise disruption, the city’s contractors will be making adjustments to the Rokeby Road irrigation system and also levelling the ground underneath the planter boxes.
Works will take place along the median strip, with no earthworks or excavations involved. Traffc management will be in place, and access to footpaths and alfresco areas will continue as normal.
Planned work schedule:
Section
|
Expected dates
|
Affected lane
|
Roberts Road to Seddon Street
|
9, 12 February
|
Northbound
|
Seddon Street to Hay Street
|
7-8 February
|
Northbound
|
Hay Street to Churchill Avenue
|
5-6 February
|
Southbound
|
Churchill Avenue to Barker Road
|
13, 15, 16 February
|
Northbound
|
Barker Road to Bagot Road
|
19-21 February
|
Southbound
|
For project enquiries, please contact Kirk Linares on 9387 0912.