Water Corporation works

The Water Corporation are currently working on the following projects in the City of Subiaco

  • Main drain upgrade

  • Water Main upgrade (pipes for Perth)

Main Drain Upgrade (December 2017 to May 2018)

The Subiaco main drain was installed over 100 years ago and due to development of the area over the last century the local drainage systems no longer have the capacity to protect local homes and businesses against flooding during large storm events.

The new drain will be constructed under the north side of the road on Churchill Ave between Townshend Road and Axon Street. This drain will fill with storm water during major storm events and allows the water to then soak into the soil, rather than conveying water through the traditional drainage system.

Preliminary work on the main drain upgrade began in early December 2017 and construction works commenced in early January 2018.  The works will take approximately four months to complete. A full road closure will be in place for the duration of the project, with access available to local traffic only. 
 
For project details and updates please visit the Water Corporation website

If you have any questions or concerns about the impact of this essential work on your home, business, or commute. Please email Water Corporation's Community Engagement Officer, Sarah Bennett at sarah.bennett@watercorporation.com.au or (08) 9420 2587 (office hours).

Water main upgrade

Water Corporation are curretnly upgrading the water main along Coghlan Road between Roberts and Subiaco Roads. Construction is now complete and the newly installed main is expected to be connected into the wider water network in December and January. For further details please visit the Water Corporation website.