City of Subiaco - Lake Jualbup upgrade
iconSubiaco WA – 18.9˚
Mostly Sunny

Lake Jualbup upgrade

This page provides an overview of the Lake Jualbup upgrade project currently being undertaken. For a comprehensive overview of work-to-date the city and other stakeholders in relation to maintaining an adequate permanent body of water in Lake Jualbup, please visit the Lake Jualbup page.  

Project overview

Council has allocated $1.4 million in the 2017/2018 budget for works to make a significant improvement to the lake and surrounds. The city will be working to minimise the impact to the adjacent residents and visitors to the lake. It is anticipated that works will be delivered in full during the 2017/18 financial year. 

Start: 27 November 2017
Expected completion: April 2018

These works aim to enhance the lake’s ecological value and public amenity and will be staged in two zones:

  • Zone 1 - lake hydrology  - western side wall replacement

  • Zone 2 - lake foreshore - northern side wall removal and creation of sloping embankment

Project update - 16 April 2018

Works at Lake Jualbup are on track for completion by the end of April. The new retaining wall and footpath fronting the lake have been completed. A new access path to the public toilet has also been added.

2500 square metres of fresh turf is now being laid and planting will soon begin on the water banks and within a newly mulched area adjacent to the footpath. The lake will refill naturally with the winter rainfall. Thank you for your patience as we complete these works.

Project update - 5 April 2018

The Lake Jualbup upgrade is on track to reach practical completion by Friday 20 April, weather permitting. Current and remaining works include footpaths, planting and reticulation and turf reinstatement works. The city has added a footpath between the lake and the public toilet near Evans Street and Herbert Road. This connection will provide improved disability access at the park.
 
The presence of botulism has been confirmed in recently deceased wildlife at the park. This is caused by a common, naturally occurring, soil-borne bacterium found in wetland environments across Perth. The city will continue to monitor water quality as it returns to normal.

Project update - 6 March 2018

A new contractor has been appointed to complete the construction works at the lake after former contractor BCL Group suspended trading. Civcon has mobilised on site and works recommenced today. The estimated completion date for the project is 12 April.

The City of Subiaco is continuing to investigate the cause of the wildlife deaths at Lake Jualbup together with the Parks and Wildlife Service, the Department of Water and Environmental Regulation and the Department of Primary Industries and Regional Development.

The cause of the deaths has not yet been established and further testing is taking place.
 
City staff will continue to monitor the lake and wildlife. For more informaiton please see the city's latest news update.

Project update - 21 February 2018

On Friday 16 February site contractors BCL stopped work at the site. Works at Lake Jualbup have paused as the city investigates environmental issues and appoints a new contractor to complete the $1.4 million upgrade project. Of immediate concern to the city is a loss of wildlife recorded on Tuesday 19 and Wednesday 20 February.

The cause of the wildlife deaths had not yet been determined and City staff are working with environmental authorities to identify the source of the problem and protect the turtles, birds and other wildlife at the lake.

Limited emergency construction works will recommence tomorrow. For more informaiton please see the city's news update.

Project update - 6 February 2018

Works at Lake Jualbup are progressing well with dewatering activities ongoing within Zones 1 and 2. The construction of the new wall in Zone 1 has commenced and is currently 20% complete with backfilling works planned within the next few days. The removal of the existing Zone 2 wall is now complete and works on the sloping embankment will be commencing soon.

Aboriginal ground monitoring and environmental management of the works continue to progress well. 

For further information on the progress or scope of works, please contact Luke McGuirk, Senior Project Engineer, on 0416 561 707. 

Project update - 23 January 2018

The Lake Jualbup project has been delayed by approximately ten working days as a result of the storm event experienced on Monday 15 January 2018 which caused heavy rainfall across Perth. The revised project completion is now scheduled for mid-April 2018.  
 
Additional dewatering works are currently in progress with other works such as the preparation of the wall foundation to start within the next few days. Other activities including Aboriginal ground monitoring and environmental management of the works continue to progress well. 

For further information on the progress or scope of works, please contact Luke McGuirk, Senior Project Engineer, on 0416 561 707. 

Project update - Monday 11 December 2017

The Lake Jualbup upgrade works commenced on 27 November 2017 with site set-up for both zones now complete. Temporary fencing with 100% block out shadecloth has been installed around the works zones to minimise sand and dust drift.

DSC_0264-(1).JPG

Works undertaken so far include stripping of topsoil adjacent to the existing wall, vegetation removal and arrival of the clay for the zone 2 embankment. Safe clearance zones have been installed around the remaining trees. Large sandbags are being filled to be used in the dewatering process that is now underway. Dewatering will create a temporary dry section at the lake edge to allow access to the walls. This process is being closely monitored by wildlife consultants, the city’s anthropologist and Aboriginal ground monitors.

The anticipated duration of works to complete both zones 1 and 2 is 12 weeks, and we are on track for the anticipated completion by March 2018.
 
For further information on the progress or scope of works, please contact Luke McGuirk, Senior Project Engineer, on 0416 561 707. 

Project details


Zone 1 – lake hydrology - western side wall replacement

Due to concerns with loss of water within the lake and subsequent investigations that revealed water infiltration through the western wall, a new limestone block retaining wall will be constructed approximately 1.2 metres to 1.4 metres high to replace the existing wall. In addition a section of the existing lake bed adjacent to the wall will be replaced with a natural clay layer to further reduce the likelihood of infiltration.
 
To accommodate the new wall, modifications to the existing drainage infrastructure will be undertaken. The Water Corporation outlet on the north west section of the lake will not be subject to any alteration in terms of changing the outlet invert levels, and the new limestone retaining wall will transition into the Water Corporation outlet structure. A new footpath of 100 mm thickness will also be constructed along the top of the wall to provide for connectivity to either side of the reserve.

Due to the close proximity of the existing Salix babylonica (weeping willow) trees behind this section of wall, a number of these trees will be removed as part of the lake upgrade. The root systems of these trees are currently protruding through the wall and into the lake bed causing damage to the wall and lake bed. New native shade trees will be planted in more appropriate locations at this end of the park. 

Zone 2 – lake foreshore - northern side wall removal and creation of sloping embankment

The existing northern retaining wall will be removed and replaced with a sloped embankment with extensive planting within both the water body and to the embankment. A gradient of 1 in 5 has been adopted, which limits erosion, and the plantings will further reduce erosion, provide habitat and grazing for wildlife and improve the aesthetics of the lake. The lake bed, between 7 and 7.5 metres in front of the face of the existing retaining wall, will also be lined with natural clay to minimise infiltration on the lake bed.

Additional information

 

Approvals

The planning phase for this project has been ongoing for many years with significant work undertaken by city staff, community stakeholders and consultants to gain the necessary environmental approvals, including a Section 18 Minister's Consent under the Aboriginal Heritage Act 1972 and a comprehensive Management Plan.

Future works

Following completion of Zones 1 and 2 future works will include upgrade of the path network, lighting and irrigation. Further liaison with the community will take place before the commencement of this work.

Work site

Safety fencing and temporary access tracks will be installed as part of these works. The contractor (BCL Group) will ensure construction machinery and staff amenities are located within the fenced construction zone, which will be located on the western side of the reserve. For safety reasons, park users will not be able to access the construction area. The fence will be infilled with mesh to screen the works and ensure sand and dust drift is minimised.  

Section 18
To ensure that the city meets the conditions stipulated for Section 18 Consent under the Aboriginal Heritage Act 1972, the city has appointed an anthropologist who will coordinate daily attendance by two Aboriginal ground monitors to observe the works where ground disturbance is necessary.  

Work hours
Construction will take place between the hours of 7:00am to 5:00pm Monday to Friday. To assist in completing the works as soon as possible the contractor has also been granted permission to work on Saturdays, subject to prior approval by the city. 

Environmental considerations

The City of Subiaco will take all care to ensure nesting sites, turtles, waterbirds and other wildlife are not adversely impacted upon during this work. A native wildlife management plan will be in place to mitigate the impact on the native wildlife during construction. An environmental consultant will work with the city and the contractor throughout construction to ensure there is no adverse impact on the lake and surrounds wildlife.

The spread of dust from the site will be mitigated by the fence mesh and construction noise will be compliant with Australian noise control standards and only occur during the work hours set out above.

Further information

The city is eager to undertake construction in a timely manner with minimal impact on the adjacent residents’ amenity.  If you wish to discuss the project further please contact Kanwal Singh, Principal Engineer (Design and Delivery), on kanwals@subiaco.wa.gov.au or 9387 0951, or Luke McGuirk, Senior Project Engineer, on lukem@subiaco.wa.gov.au or 9387 9934. 


New-Picture.png